With the SIMATIC S7-300 now in its phase-out, many plants are asking the same question: when and how should we move to S7-1500? This guide walks through the reasons to migrate, how to prepare, and the migration process we follow on real projects.
Why move to S7-1500 and TIA Portal?
The S7-1500 and the TIA Portal engineering environment are Siemens’ current platform for PLC automation. Compared with S7-300/400 and STEP 7 Classic, they offer:
- Higher performance — faster processing for demanding machine and process applications.
- One integrated engineering environment — PLC, HMI, drives and networks configured in a single TIA Portal project.
- Integrated diagnostics — system diagnostics are displayed on the CPU, in TIA Portal and on the HMI without extra programming.
- Integrated security — know-how protection, copy protection and access levels built in.
- Integrated technology — motion control, PID and trace functions available out of the box.
- Long-term support — staying on the current platform protects you from rising spare-part prices and shrinking support for older hardware.
Before you start: preparation
A successful migration is mostly decided before any hardware is changed.
- Document the existing system. Record every CPU, I/O module, communication processor and network, plus all connected devices — drives, HMIs, remote I/O and third-party equipment.
- Collect and back up the software. Upload the running program from every PLC, archive the STEP 7 projects, libraries and HMI projects, and keep a restorable backup of the original state.
- Check what you really have. The program on the CPU and the project on the laptop are often not the same. Compare them before you migrate anything.
- Write a migration plan. Define the scope, the shutdown window, responsibilities, test criteria and a fallback plan in case something goes wrong on site.
The migration process
- Set up the engineering workstation with the current TIA Portal version and the required options and licences.
- Migrate the STEP 7 Classic project into TIA Portal using the built-in migration function, then change the hardware configuration to the new S7-1500 CPU and I/O.
- Review and adapt the program. Migrated code compiles, but it rarely takes full advantage of the new platform. Instructions, addressing, timers, communication blocks and system functions often need attention.
- Re-engineer the HMI where needed — older panels may need to move to current Comfort or Unified panels.
- Simulate and test offline using PLCSIM and a structured test plan before going to site.
- Install and commission during the planned shutdown, keeping existing field wiring wherever possible.
- Validate, train and document. Prove every function against the test plan, train operators and maintenance staff, and hand over updated drawings and backups.
Tip: wherever possible, build and test the new panel in parallel so the site shutdown is used for change-over, not debugging.
After the migration
- Keep firmware and TIA Portal versions up to date and documented.
- Schedule regular backups of PLC, HMI and drive parameters.
- Collect feedback from operators and maintenance — the first weeks after a migration are the best time to fine-tune alarms and screens.
Need help?
Technotude has migrated legacy Siemens systems — from S5 through S7-300/400 — to current platforms on running machines. Talk to our engineers about your S7-300 or S7-400 migration, or read about our retrofit approach.