4Hi Rewinder — Siemens S5 to S7-1200 & 6RA80 retrofit

An obsolete Siemens S5 PLC and Emerson DC drives replaced with a Siemens S7-1200 CPU and Siemens 6RA80 DC drives in a new, fully documented control panel.

OLD SYSTEM

Siemens S5 PLC · Emerson DC drives

NEW SYSTEM

Siemens S7-1200 CPU · Siemens 6RA80 DC drives

technotude AUTOMATION PVT. LTD.
DOC NO.
TT-CS-01
MACHINE
4Hi Rewinder
SECTION
PLC & DC drive system
INDUSTRY
Metals — strip processing
DRAWN
TECHNOTUDE AUTOMATION
REV / SHEET
A · 1 OF 1
BEFORE

Siemens S5 PLC · Emerson DC drives

  • Siemens S5 control system — obsolete since 2005
  • Ageing Emerson DC drives with limited support
  • Congested, poorly documented legacy wiring
AFTER

Siemens S7-1200 CPU · Siemens 6RA80 DC drives

  • Current-generation Siemens S7-1200 controller
  • Siemens SINAMICS DC Master 6RA80 drives
  • New panel with structured, labelled wiring

The challenge

The 4Hi rewinder was mechanically sound, but its control system was not. It ran on a Siemens S5 PLC — a platform Siemens declared obsolete in 2005 — together with Emerson DC drives. Spare parts were getting scarcer and more expensive, and every breakdown carried the risk of extended downtime.

Years of modifications had also left the cabinet with congested, poorly documented wiring, making fault-finding slow for the maintenance team.

Our solution

Rather than replacing the machine, we retrofitted the control and drive section:

  • Surveyed the existing system, I/O and field wiring to define exactly what could be re-used.
  • Designed and built a new control panel around a Siemens S7-1200 CPU.
  • Migrated the S5 control logic to the S7 platform and documented it fully.
  • Kept the DC motors and upgraded the drives to Siemens 6RA80 DC converters, engineered and tuned for the rewinder.
  • Installed and commissioned the new system on site, then handed over complete documentation.

The result

The rewinder now runs on current, fully supported Siemens hardware with modern diagnostics, clean labelled wiring and complete documentation — extending the life of the machine without the cost and disruption of buying a new one.

TT-99 Start a project

Got an obsolete PLC, a tired drive, or a new line to automate?

Start a work order. An engineer — not a call centre — reviews every enquiry and responds within one business day.